Why Mathematics? | Condition Monitoring: Degradation Signals, Thresholds, False Alarms and Remaining Useful Life

Why is mathematics important in condition monitoring? Sensors produce noisy measurements; mathematics helps distinguish normal variation from degradation, set thresholds, count false alarms and express remaining useful life as an uncertain forecast rather than a fixed date.

Did You Know? Even a monitor with 90% sensitivity and 95% specificity can produce more false than true alerts when real degradation is uncommon.

Full chapter index

Chapters 1–7 · Understand the question
  1. Why condition monitoring needs mathematics
  2. From measurement to decision
  3. Detection, diagnosis and prognosis
  4. NASA and NIST context
  5. A degradation signal
  6. A simple remaining-life calculation
  7. Remaining useful life is conditional
Chapters 8–14 · Reproduce the example
  1. Thresholds and trade-offs
  2. A base-rate example
  3. Positive predictive value
  4. False negatives
  5. Measurement error and calibration
  6. Sampling and aliasing
  7. Smoothing and delay
Chapters 15–21 · Check assumptions
  1. Change detection
  2. Operating regimes
  3. Feature engineering
  4. Model validation by asset and time
  5. Rare failures and imbalance
  6. Uncertainty calibration
  7. Alarm management
Chapters 22–28 · Explore applications
  1. Maintenance thresholds
  2. Data drift
  3. Causal limits
  4. Digital twins and models
  5. A student investigation
  6. A spreadsheet workflow
  7. A coding workflow
Chapters 29–45 · Study and verify
  1. Applications and careers
  2. Guidance for students and parents
  3. Common misconceptions
  4. Connection to recent mathematics articles
  5. Practice questions
  6. Frequently asked questions
  7. A reporting checklist
  8. A final audit
  9. Useful next reading
  10. Sampling rate and aliasing
  11. Change-point detection
  12. Survival models with sensor covariates
  13. Fleet learning and asset differences
  14. Decision thresholds and maintenance capacity
  15. Monitoring the monitor
  16. Student investigation
  17. Calibration of predicted risk and remaining life

CHAPTER 1 OF 45 · Understand the question

1. Why condition monitoring needs mathematics

Back to contents

Condition monitoring uses measurements to ask whether equipment or a process is healthy, degrading or approaching a functional limit. Mathematics turns noisy signals into evidence, while keeping detection, diagnosis, prognosis and maintenance action distinct. A trend line can support a decision only when sensors, thresholds, operating context and uncertainty are understood. The goal is timely, justified action rather than a dashboard full of confident-looking numbers.

Contents · Next chapter

CHAPTER 2 OF 45 · Understand the question

2. From measurement to decision

Back to contents

A sensor records vibration, temperature, current, pressure, wear or another proxy. A feature extracts information, a model estimates state, an alarm applies a rule, and an authorised process decides what to do. These steps are not interchangeable. A high reading can be real degradation, normal load change, sensor drift or data error. Preserve the chain so investigators can identify where a false alarm or missed detection arose.

Contents · Previous chapter · Next chapter

CHAPTER 3 OF 45 · Understand the question

3. Detection, diagnosis and prognosis

Back to contents

Detection asks whether behaviour changed. Diagnosis asks which fault or mechanism is likely. Prognosis estimates future condition or remaining useful life. A model can detect change without knowing the cause, or diagnose a fault without predicting when it becomes unacceptable. Reports should name the task. Calling every alert predictive maintenance exaggerates what the mathematics has established.

Contents · Previous chapter · Next chapter

CHAPTER 4 OF 45 · Understand the question

4. NASA and NIST context

Back to contents

NIST’s Prognostics, Health Management and Control programme develops measurement science for robust sensing, diagnostics and prognostics. Read the NIST PHMC overview. NASA describes condition monitoring as a basis for maintenance decisions and cautions that unnecessary intervention can add risk. Read NASA hardware and condition-monitoring guidance.

Contents · Previous chapter · Next chapter

CHAPTER 5 OF 45 · Understand the question

5. A degradation signal

Back to contents

A useful signal changes in a repeatable relationship with the target condition before functional failure. Vibration amplitude may increase with bearing damage, but also with speed and load. Temperature can rise with friction or ambient conditions. Transform or normalise features using known operating covariates. A correlation in historical data is not enough; the signal should have a plausible mechanism and stable measurement process.

Contents · Previous chapter · Next chapter

CHAPTER 6 OF 45 · Understand the question

6. A simple remaining-life calculation

Back to contents

Suppose a degradation indicator is 40 units, the functional threshold is 55, and a simplistic linear trend is 0.5 unit per day. The point estimate of remaining time is (55-40)/0.5=30 days. This result assumes constant slope, correct threshold and no measurement error. It is a teaching example, not a maintenance instruction. Real RUL should be a distribution that changes as new observations arrive.

Actual stateAlertNo alert
Degraded: 50455
Not degraded: 95047.5 expected902.5 expected
Total92.5 expected907.5 expected
Illustrative alarm base-rate table.

Contents · Previous chapter · Next chapter

CHAPTER 7 OF 45 · Understand the question

7. Remaining useful life is conditional

Back to contents

RUL means time until a defined end-of-useful-life event, conditional on current information and future operating assumptions. Change the load profile, threshold or degradation model and the distribution changes. Report prediction intervals or quantiles, not only a date. A unit can fail through another mode before the monitored indicator reaches its limit. RUL is a model output tied to a definition, not a hidden clock inside the asset.

Contents · Previous chapter · Next chapter

CHAPTER 8 OF 45 · Reproduce the example

8. Thresholds and trade-offs

Back to contents

Lowering an alarm threshold can detect more true problems earlier but creates more false alarms. Raising it reduces alarm burden but can miss degradation or shorten response time. Receiver-operating-characteristic and precision-recall curves describe parts of this trade-off. Choose the threshold from consequence, prevalence, lead time and response capacity. An accuracy maximum may be inappropriate when missed failures and unnecessary shutdowns have very different costs.

Contents · Previous chapter · Next chapter

CHAPTER 9 OF 45 · Reproduce the example

9. A base-rate example

Back to contents

Among 1,000 checks, suppose 5% are truly degraded. With 90% sensitivity, 45 of 50 degraded cases alert. With 95% specificity, 5% of 950 healthy cases, or 47.5 in expectation, also alert. Thus fewer than half the alerts are true in this illustration. A good test can still produce many false alarms when the condition is uncommon. Expected counts may be fractional; observed counts are integers.

Contents · Previous chapter · Next chapter

CHAPTER 10 OF 45 · Reproduce the example

10. Positive predictive value

Back to contents

The illustrative positive predictive value is 45/(45+47.5), about 48.6%. This is the probability that an alert corresponds to the defined degraded state under the assumed prevalence and performance. If prevalence changes across sites or seasons, predictive value changes even when sensitivity and specificity remain constant. Report the operating population and avoid transporting one alert-quality percentage everywhere.

Contents · Previous chapter · Next chapter

CHAPTER 11 OF 45 · Reproduce the example

11. False negatives

Back to contents

Five degraded cases in the illustration do not alert. Review missed detections by failure mode, operating state and sensor quality. A model can miss sudden failures that have no gradual precursor. Safety-critical controls should not rely on a prognostic signal without authorised hazard analysis and independent protections. Monitoring can support risk reduction, but absence of an alarm is not proof of health.

Contents · Previous chapter · Next chapter

CHAPTER 12 OF 45 · Reproduce the example

12. Measurement error and calibration

Back to contents

Sensor bias, drift, noise, mounting and sampling rate affect every downstream result. Calibration checks measure some aspects but may not reproduce field installation. Use reference signals, redundancy and plausibility rules. Store raw data and quality flags. If an algorithm silently imputes missing values, the confidence output should reflect that. A precise forecast from a drifting sensor is precise misinformation.

Contents · Previous chapter · Next chapter

CHAPTER 13 OF 45 · Reproduce the example

13. Sampling and aliasing

Back to contents

A vibration signal sampled too slowly can make high-frequency behaviour appear at a false lower frequency. Irregular sampling can distort trends and spectral features. Choose sampling rate from the physics and anti-aliasing requirements. Synchronise clocks across sensors. Downsampling may save storage but remove short transients that matter. Document preprocessing so a result can be reproduced from the original waveform.

OutputMeaning
DetectionA change may be present
DiagnosisA likely fault mode
PrognosisA future state or RUL distribution
AlarmA rule has triggered
Maintenance actionA governed operational decision
Condition-monitoring outputs.

Contents · Previous chapter · Next chapter

CHAPTER 14 OF 45 · Reproduce the example

14. Smoothing and delay

Back to contents

Moving averages and filters reduce noise but delay or attenuate changes. A longer window can make a chart calm while postponing an alarm. Quantify step response and phase delay for the feature. Compare raw and filtered signals during known events. Filtering is part of the model, not cosmetic presentation. A threshold validated on one filter cannot be moved to another without revalidation.

Contents · Previous chapter · Next chapter

CHAPTER 15 OF 45 · Check assumptions

15. Change detection

Back to contents

Control charts, cumulative sums and Bayesian change-point methods can flag shifts. Their false-alarm properties depend on assumptions about baseline variation and independence. Set a stable baseline by operating regime. A change signal starts investigation; it does not diagnose a component automatically. When many sensors are monitored, multiple-alert burden and correlation matter. Combine statistics with physical context.

Contents · Previous chapter · Next chapter

CHAPTER 16 OF 45 · Check assumptions

16. Operating regimes

Back to contents

Load, speed, product type, ambient temperature and maintenance state can change normal signals. A global threshold may alarm during legitimate high-load operation and miss damage at low load. Stratify, normalise or model regimes explicitly. Ensure every regime has enough validation data. A model trained mainly on steady operation may fail during startup and shutdown, which are often the moments of greatest interest.

Contents · Previous chapter · Next chapter

CHAPTER 17 OF 45 · Check assumptions

17. Feature engineering

Back to contents

Features can include time-domain statistics, frequency peaks, envelopes, rates of change or learned representations. Each compression discards information. Prefer features that remain stable across sensors and connect to failure mechanisms. Avoid selecting hundreds of features on a small data set without proper validation. Feature importance from a predictive model does not establish causality. Record units and transformations.

Contents · Previous chapter · Next chapter

CHAPTER 18 OF 45 · Check assumptions

18. Model validation by asset and time

Back to contents

Randomly splitting individual rows can leak nearly identical measurements from one asset into training and test sets. Hold out entire assets, later time periods or sites according to the intended deployment. Prevent future measurements from entering current features. Compare with simple baselines. Report performance by failure mode and operating regime, not only one average score. Validation should imitate the decision environment.

Contents · Previous chapter · Next chapter

CHAPTER 19 OF 45 · Check assumptions

19. Rare failures and imbalance

Back to contents

Most monitoring data may be healthy, while failure examples are rare and selected. Overall accuracy can be high if a model predicts healthy every time. Use precision, recall, false alarms per operating time and lead-time distributions. Synthetic faults may help development but need field confirmation. A model cannot learn every unknown failure mode from labels that do not exist.

Contents · Previous chapter · Next chapter

CHAPTER 20 OF 45 · Check assumptions

20. Uncertainty calibration

Back to contents

A 90% prediction interval should contain the future target about 90% of the time in comparable cases if calibrated. Check coverage across horizon, asset and regime. Narrow intervals are not useful if wrong. Separate aleatory variability from parameter and model uncertainty when helpful. If the asset is outside the training domain, widen uncertainty or abstain. Confidence should guide action, not decorate the dashboard.

Contents · Previous chapter · Next chapter

CHAPTER 21 OF 45 · Check assumptions

21. Alarm management

Back to contents

An alarm needs priority, owner, response time, evidence and closure criteria. Too many false alarms cause fatigue and delay. Track alerts per asset-month, acknowledgement, action, confirmed findings and repeated alerts. Suppression rules can hide real events if poorly governed. Design the human workflow with the algorithm. A model that scores well offline can fail operationally when the organisation cannot respond.

Contents · Previous chapter · Next chapter

CHAPTER 22 OF 45 · Explore applications

22. Maintenance thresholds

Back to contents

An alert threshold and a maintenance threshold may differ. An early alert can trigger inspection, while a later condition triggers shutdown or replacement. Define escalation and confirmation. Incorporate access windows, spare availability and consequence. Do not turn an uncertain RUL point estimate into an automatic work order unless the decision process is validated and authorised. Human review can be part of a safe system.

Contents · Previous chapter · Next chapter

CHAPTER 23 OF 45 · Explore applications

23. Data drift

Back to contents

Sensors, assets, software and operating practices change. Monitor feature distributions, missingness and outcome relationships. A stable average error can hide deterioration in one regime. Recalibration or retraining needs version control and independent evaluation. Never train on labels created by the model’s own earlier alerts without checking feedback bias. Preserve a champion baseline and rollback path.

Contents · Previous chapter · Next chapter

CHAPTER 24 OF 45 · Explore applications

24. Causal limits

Back to contents

A feature that predicts failure may be a consequence, shared cause or operational response. Changing it may not prevent failure. Maintenance decisions need mechanism evidence and intervention studies where feasible. Correlation can still be useful for prediction, but language must remain precise. Say the signal is associated with risk rather than claiming it causes damage unless the evidence supports causation.

Contents · Previous chapter · Next chapter

CHAPTER 25 OF 45 · Explore applications

25. Digital twins and models

Back to contents

A physics-based or hybrid digital twin can estimate hidden state and simulate future paths. Its usefulness depends on parameter identification, boundary conditions and model discrepancy. Updating a twin with sensor data does not remove structural error. Validate predictions against held-out assets and abnormal regimes. A visually realistic twin can still be mathematically wrong. Report which parts are measured, estimated and assumed.

Contents · Previous chapter · Next chapter

CHAPTER 26 OF 45 · Explore applications

26. A student investigation

Back to contents

Use a simulated signal that rises toward a threshold with random noise. Calculate a moving average, trigger alarms and estimate RUL with a line. Change the window and threshold, then count early, late and false alarms. Add a sensor bias. Students learn rates, graphs, probability and model limits. The exercise should not control real equipment or imply professional maintenance advice.

Contents · Previous chapter · Next chapter

CHAPTER 27 OF 45 · Explore applications

27. A spreadsheet workflow

Back to contents

Create columns for time, operating regime, raw signal, quality flag, filtered feature, threshold, alarm and confirmed state. Calculate confusion-matrix counts and predictive value. Fit a simple slope only over a documented window, then compute an illustrative RUL and sensitivity to slope. Plot raw and filtered data together. Keep failure threshold and maintenance action separate. Label all simulated values.

Contents · Previous chapter · Next chapter

CHAPTER 28 OF 45 · Explore applications

28. A coding workflow

Back to contents

Build time-aware pipelines that prevent leakage. Unit-test sampling, missing-data rules, filter delay and threshold boundaries. Split by asset and time. Return calibrated intervals and abstention flags. Log model, sensor and feature versions with every prediction. Reproduce the base-rate table and linear example independently. Review deployment code for alarm flooding and stale data, not only model accuracy.

Contents · Previous chapter · Next chapter

CHAPTER 29 OF 45 · Study and verify

29. Applications and careers

Back to contents

Condition monitoring supports manufacturing, transport, energy, buildings, robotics and computing infrastructure. Roles combine mathematics, signal processing, engineering, statistics, machine learning and maintenance knowledge. Mathematics creates options but does not guarantee a job or salary. Students can explore graphs and probability, then consider engineering, data science, computing or technical programmes using current official pathway information.

Contents · Previous chapter · Next chapter

CHAPTER 30 OF 45 · Study and verify

30. Guidance for students and parents

Back to contents

Students should distinguish a measurement, an alarm and a decision. Reproduce the thirty-day point estimate, then list every assumption that could change it. Parents can use the base-rate example to discuss why a good test can have many false alarms. Practise on synthetic data. The transferable lesson is that prediction is useful when uncertainty, context and action are designed together.

Contents · Previous chapter · Next chapter

CHAPTER 31 OF 45 · Study and verify

31. Common misconceptions

Back to contents

An alert is not a diagnosis. No alert is not proof of health. RUL is not a fixed countdown. Smoothing can add delay. High accuracy can hide rare-failure misses. A threshold that works in one regime may fail in another. More sensors do not automatically create more information. A predictive association does not prove a cause. Condition monitoring does not replace safety controls.

Contents · Previous chapter · Next chapter

CHAPTER 32 OF 45 · Study and verify

32. Connection to recent mathematics articles

Back to contents

Read Preventive Maintenance Optimisation for policy choices, Measurement System Analysis for sensor quality and Availability Engineering for service impact. The Mathematics Learning Hub links graphs, statistics and computing.

Contents · Previous chapter · Next chapter

CHAPTER 33 OF 45 · Study and verify

33. Practice questions

Back to contents

1. Calculate the linear RUL example. 2. Build the 1,000-check confusion matrix. 3. Find positive predictive value. 4. Explain base-rate effects. 5. Give one smoothing delay. 6. Describe sensor drift. 7. Prevent one data-leakage path. 8. Distinguish detection and diagnosis. 9. Propose an abstention rule. 10. Write a cautious maintenance recommendation.

Contents · Previous chapter · Next chapter

CHAPTER 34 OF 45 · Study and verify

34. Frequently asked questions

Back to contents

### Is RUL the exact failure date? No. It is a conditional prediction distribution tied to assumptions.

### Why are many alerts false? Low prevalence and imperfect specificity can produce many false positives.

### Does filtering always help? It reduces some noise but can delay or distort changes.

### Can AI replace engineering review? A model can support decisions, but governance, mechanisms and authorised review remain necessary.

Contents · Previous chapter · Next chapter

CHAPTER 35 OF 45 · Study and verify

35. A reporting checklist

Back to contents

Define asset, function, signal, units, sampling, regimes, threshold and end-of-life event. Report sensor quality, preprocessing, validation split, prevalence, sensitivity, specificity, false alarms, misses, lead time and RUL interval calibration. State action and escalation rules. Monitor drift. Link primary sources. Avoid causal or safety claims beyond the evidence and never present a point forecast as certainty.

Contents · Previous chapter · Next chapter

CHAPTER 36 OF 45 · Study and verify

36. A final audit

Back to contents

Recalculate 30 days, 45 true alerts, 47.5 expected false alerts and 48.6% predictive value. Confirm observed counts are integers. Inspect units, clocks, filter delay and threshold direction. Test leakage and asset-level splits. Verify source links. Remove claims that an alarm proves a fault, that RUL is fixed or that condition monitoring alone guarantees safe operation.

Contents · Previous chapter · Next chapter

CHAPTER 37 OF 45 · Study and verify

37. Useful next reading

Back to contents

Continue with NIST PHMC research, NASA condition-monitoring and reliability-centred maintenance guidance, and work on calibrated prognostics. Compare the topic with measurement system analysis, preventive maintenance and Markov reliability. The Mathematics Learning Hub connects rates, time series, probability, classification and uncertainty.

Contents · Previous chapter · Next chapter

CHAPTER 38 OF 45 · Study and verify

38. Sampling rate and aliasing

Back to contents

A sensor sampled too slowly can miss or misrepresent a changing signal. Relate the sampling interval to the physical frequencies of interest, anti-alias filtering and storage constraints. Faster sampling creates more data but may add little information when the sensor bandwidth or failure process is slow. Validate the full measurement chain. A smooth trend produced after aliasing is not faithful evidence, and a high-rate stream does not compensate for poor placement or calibration.

Contents · Previous chapter · Next chapter

CHAPTER 39 OF 45 · Study and verify

39. Change-point detection

Back to contents

Some degradation begins as a step or shift rather than a steady slope. Change-point methods compare evidence for a stable regime with evidence that model parameters changed. Define the false-alarm rule, minimum detectable change and delay metric. Test the method on labelled events and realistic stable periods. A detected change says the statistical behaviour altered; engineering diagnosis still has to determine whether the cause is wear, maintenance, environment, sensor replacement or data processing.

Contents · Previous chapter · Next chapter

CHAPTER 40 OF 45 · Study and verify

40. Survival models with sensor covariates

Back to contents

Time-to-event models can use condition measurements as covariates, but time-varying data require careful alignment. Avoid using measurements collected after the prediction time. Check proportional-hazards or other structural assumptions and compare calibration across assets and operating regimes. A risk score is not automatically a remaining-life estimate. Present predicted survival probabilities at relevant horizons with uncertainty and a clear reference population.

Contents · Previous chapter · Next chapter

CHAPTER 41 OF 45 · Study and verify

41. Fleet learning and asset differences

Back to contents

Pooling a fleet can improve precision, yet assets differ by age, duty cycle, installation and maintenance. Hierarchical models allow shared learning while preserving asset-level variation. Hold out whole assets and later time periods when testing generalisation. If only the best-instrumented machines provide data, selection bias may hide difficult cases. Report where the model works, where it is uncertain and whether recalibration is required after operating changes.

Contents · Previous chapter · Next chapter

CHAPTER 42 OF 45 · Study and verify

42. Decision thresholds and maintenance capacity

Back to contents

An alert threshold should connect to an action, response time and available capacity. Combine false-alarm and missed-detection consequences with inspection cost and lead time. A theoretically optimal threshold may fail operationally if it creates more work orders than technicians can investigate. Simulate alert queues and escalation rules. Governance should allow human review and safe fallback when data are missing or contradictory.

Contents · Previous chapter · Next chapter

CHAPTER 43 OF 45 · Study and verify

43. Monitoring the monitor

Back to contents

After deployment, track calibration, alert rate, confirmation rate, missed events, latency and data completeness. Compare these measures by site, asset class and season. Detect changes in sensor distribution and model performance before they create unsafe confidence. Version the model and thresholds, preserve an audit trail and define who can approve changes. Condition monitoring is a continuing measurement process, not a one-time model launch.

Contents · Previous chapter · Next chapter

CHAPTER 44 OF 45 · Study and verify

44. Student investigation

Back to contents

Collect a harmless time series such as battery voltage or a simulated wear signal. Add noise, drift and a known threshold. Compare raw values, a moving average and a fitted trend. Measure how smoothing changes alarm timing. Use repeated simulations to form an RUL distribution, then report median and prediction interval. Explain why the experiment does not justify a real maintenance decision without validated sensors, failure thresholds and operating evidence.

Contents · Previous chapter · Next chapter

CHAPTER 45 OF 45 · Study and verify

45. Calibration of predicted risk and remaining life

Back to contents

A model can rank assets correctly and still give poorly calibrated probabilities. Group comparable predictions and compare them with observed outcomes at the stated horizon, while allowing for censoring and time dependence. For remaining useful life, examine interval coverage and error as the prediction horizon shortens. Recalibrate only with data that match the deployment population and preserve a separate evaluation set. Report both discrimination and calibration because a maintenance planner needs absolute risk, not only ordering. Where labels are delayed or uncertain, describe that limitation and use conservative governance. A model that says ten assets each have a 10% chance of failure should, over many comparable cases, be checked against roughly one observed event; individual outcomes never prove calibration. This discipline keeps forecasts honest and makes changes detectable.

Contents · Previous chapter · Mathematics Learning Hub

Extended practice laboratory

Practice case 1: Linear RUL example

Setup: Signal is 40, failure threshold 55 and trend 0.5 units/day.

Task: Calculate (55-40)/0.5.

Checking target: Obtain 30 days under a simplistic constant-trend model.

Practice case 2: Base-rate table

Setup: Use 1,000 checks, 5% degraded, 90% sensitivity and 95% specificity.

Task: Compute alert counts.

Checking target: Obtain 45 true alerts and 47.5 expected false alerts.

Practice case 3: Positive predictive value

Setup: Use the base-rate table.

Task: Calculate true alerts divided by all alerts.

Checking target: Obtain about 48.6% in the illustration.

Practice case 4: Threshold shift

Setup: Raise and lower an alarm threshold.

Task: Track false positives and false negatives.

Checking target: Recognise the trade-off.

Practice case 5: Smoothing delay

Setup: Apply a moving average.

Task: Compare noise reduction and response delay.

Checking target: Do not treat a smoother signal as free information.

Practice case 6: Sensor drift

Setup: Add a slowly changing bias.

Task: Observe its effect on threshold crossing.

Checking target: Calibration and reference checks matter.

Practice case 7: RUL distribution

Setup: Replace a point forecast with quantiles.

Task: Report median and prediction interval.

Checking target: Plan from uncertainty, not one date.

Practice case 8: Failure threshold

Setup: Define the functional threshold physically.

Task: Check whether it varies by duty cycle.

Checking target: Do not let the model invent the end of life.

Practice case 9: Data leakage

Setup: Build training and test sets by asset and time.

Task: Prevent future measurements entering features.

Checking target: Validate as the model would operate.

Practice case 10: Alarm burden

Setup: Count alerts per asset-month and response time.

Task: Include technician capacity.

Checking target: A high-sensitivity system can overload action.

Practice case 11: Missed detection

Setup: Review failures without prior alarms.

Task: Separate sensor, model and process causes.

Checking target: Use misses to improve validation.

Practice case 12: Write a decision

Setup: State signal, threshold, horizon and action.

Task: Report false alarms, misses and RUL uncertainty.

Checking target: Avoid turning prediction into certainty.