Use AI to map the dependencies between tasks before trying to make a project faster. Identify which work can run in parallel, calculate the longest required sequence and see how much delay other tasks can absorb before the project finish changes. A long task is not automatically the most urgent one, and a short task can control the whole schedule if other work depends on it.
This international guide follows Samira, a fictional coordinator preparing a small learning exhibition. All activities, durations and resource assumptions are invented. SuperIntelligence is the future-facing theme, not a claim that present AI has demonstrated general superintelligence. A schedule calculation describes the stated model; it does not guarantee a completion date or establish that the necessary people and resources are available.
- List required deliverables and dependency relationships.
- Separate task effort, elapsed duration and available resources.
- Calculate earliest start and finish times through the network.
- Find the longest path and compute available float.
- Recalculate after changed durations, dependencies or resource limits.
- Keep schedule forecasts separate from commitments and approvals.
EDUKATE · VOCABULARY CODING AND ENGINEERING · PART 92 · TWENTY-THIRD COLLECTION
Find your next useful step
Continue the series: Parts 89–92
- Part 89: Regression testing AI workflows
- Part 90: Reconciling balances and movements
- Part 91: Coding open-text observations
- Part 92: Finding the critical path and schedule slack — you are here
Parts 85–88: sensitive assumptions, retrieval, pilots and prioritising queues · Begin the complete series
Full chapter index
Build the dependency model
Calculate the critical path
Test slack and constraints
Verify and communicate the schedule
Teach and extend project reasoning
1. Define the actual finish milestone
Samira wants a learning exhibition ready for an internal review. Completion means all required exhibit text and layout are approved and assembled. It does not include opening the exhibition to visitors or promising a public launch date.
A dependency network must model the actual outcome being planned. If a required approval or preparation step is missing, the calculated finish can be misleadingly early.
2. Distinguish duration from effort
A four-hour task may require one person’s four hours, two people working together, or waiting for an external response. Elapsed duration and person-hours are different quantities.
The fictional example uses working-hour durations and initially assumes enough suitable resources for tasks that can occur simultaneously. These assumptions matter when interpreting the result.
Contents · Previous chapter · Next chapter
3. Create the six fictional activities
A is confirm scope, duration 2 hours. B is draft exhibit text, 4 hours, after A. C is prepare layout, 3 hours, after A. D is review text, 2 hours, after B. E is assemble exhibit, 3 hours, after both C and D. F is final review, 1 hour, after E.
All dependencies are finish-to-start with no additional lag in this simple model. The schedule begins at time zero and assumes a continuous working-time calendar.
Contents · Previous chapter · Next chapter
4. Read the dependency graph
The network branches after A: one branch follows B then D; the other follows C. Both branches must be complete before E begins. F follows E and finishes the project milestone.
Ask AI to list predecessor IDs for every activity, not merely put tasks into a plausible numbered list. The branch and join determine where parallel work is possible.
Related guide: parallel work and integration.
Contents · Previous chapter · Next chapter
5. Check for missing or circular dependencies
If D depends on B and B is mistakenly made dependent on D, the two activities cannot start under the stated rules. The scheduling model has a cycle rather than a valid sequence.
Ask a responsible person to confirm which real handoffs are necessary. Do not remove a dependency just to make the software return a feasible result.
Contents · Previous chapter · Next chapter
6. Calculate earliest times forward
A starts at 0 and finishes at 2. B starts at 2 and finishes at 6. C starts at 2 and finishes at 5. D starts at 6 and finishes at 8.
E cannot start before both C and D finish, so its earliest start is max(5,8) = 8; it finishes at 11. F runs from 11 to 12. The modelled earliest finish is hour 12.
| Task | Predecessor(s) | Duration (h) | Earliest start | Earliest finish |
|---|---|---|---|---|
| A | None | 2 | 0 | 2 |
| B | A | 4 | 2 | 6 |
| C | A | 3 | 2 | 5 |
| D | B | 2 | 6 | 8 |
| E | C, D | 3 | 8 | 11 |
| F | E | 1 | 11 | 12 |
Contents · Previous chapter · Next chapter
7. Understand the join at E
C finishes at hour 5, but D finishes at hour 8. Starting assembly at hour 5 would violate the requirement that reviewed text also be ready.
At a join, the latest required predecessor determines the earliest successor start. AI can help visualise this relationship, but the actual dependency needs to be established by the people doing the work.
Contents · Previous chapter · Next chapter
8. Calculate the path lengths
Path A–B–D–E–F has duration 2 + 4 + 2 + 3 + 1 = 12 hours. Path A–C–E–F has duration 2 + 3 + 3 + 1 = 9 hours.
In this simplified unconstrained network the first is the critical path because it determines the earliest finish. The three-hour difference is potential flexibility on the shorter branch under the stated assumptions.
Contents · Previous chapter · Next chapter
9. Calculate latest times backwards
Use hour 12 as the model’s finish boundary. F must start by 11, E by 8, D by 6 and B by 2. C must finish by 8 and therefore can start as late as 5.
A must finish by the earlier of its successors’ latest starts, min(2,5) = 2, so it must start by 0. This backward pass identifies the latest feasible activity times relative to the chosen finish.
Contents · Previous chapter · Next chapter
10. Calculate total float
Total float in this simple model is latest start minus earliest start. A, B, D, E and F each have zero. C has 5 − 2 = 3 hours.
This means C can be delayed by up to three hours from its earliest start without changing the calculated finish, assuming the other durations, dependencies and resource assumptions remain unchanged.
| Task | Earliest start | Latest start | Total float (h) |
|---|---|---|---|
| A | 0 | 0 | 0 |
| B | 2 | 2 | 0 |
| C | 2 | 5 | 3 |
| D | 6 | 6 | 0 |
| E | 8 | 8 | 0 |
| F | 11 | 11 | 0 |
Related guide: prioritising queues.
Contents · Previous chapter · Next chapter
11. Do not add float across activities blindly
Several activities on a branch may share the same available path flexibility. If one consumes the slack, less remains for another. Float is not an independent savings account for every task.
In this example only C is noncritical. In a richer network, recalculate after a delay rather than assuming every displayed float value can be used simultaneously.
Contents · Previous chapter · Next chapter
12. Test a delay within the available slack
Suppose C begins at hour 4 instead of hour 2 and still takes three hours. It finishes at 7, before D’s hour-8 finish. E can still start at 8, and the project can still finish at 12.
C’s two-hour delay consumes part of its three-hour float. The revised remaining flexibility on that branch is one hour under unchanged conditions.
Contents · Previous chapter · Next chapter
13. Test a delay beyond the available slack
In a separate scenario, C starts at hour 6 and finishes at 9. D still finishes at 8. E now starts at 9, finishes at 12 and F finishes at 13.
The project finish has moved by one hour, not four. The shorter branch has become the controlling branch in this changed network with the imposed start delay.
Contents · Previous chapter · Next chapter
14. Test a delay on the original critical path
In another separate scenario, B takes five hours instead of four. B ends at 7, D at 9, E at 12 and F at 13. C still finishes at 5.
Under these assumptions the extra hour on the controlling path passes through to the finish. This helps identify where improved reliability or feasible acceleration could matter most.
Contents · Previous chapter · Next chapter
15. Recognise when two paths become critical
Suppose C takes six hours rather than three, with its earliest start unchanged at 2. It finishes at 8, exactly when D finishes. Both complete paths now have duration 12.
Neither branch has spare time before the join in that scenario. A delay on either can postpone the project. Critical paths can change when durations or dependencies change.
Contents · Previous chapter · Next chapter
16. Add the real resource constraint
Suppose one person must perform both B and C and cannot work on them simultaneously, while D has a separate reviewer. The unconstrained forward calculation is no longer a feasible schedule.
If that person does B from 2 to 6 and C from 6 to 9, D runs from 6 to 8; E starts at 9 and F ends at 13, assuming other resources are available. Resource sequencing has changed the finish.
Related guide: finding bottlenecks.
Contents · Previous chapter · Next chapter
17. Compare another feasible resource sequence
If the same person does C from 2 to 5 and B from 5 to 9, D finishes at 11, E at 14 and F at 15. Under the stipulated resource constraints this is two hours later than B-first sequencing.
These are two possible schedules under a simple constraint. A larger resource-constrained network may require specialist methods; an unconstrained critical path alone may not determine the best feasible plan.
Contents · Previous chapter · Next chapter
18. Give AI a bounded scheduling brief
Try: Here are task IDs, durations, predecessors, resource restrictions and the finish definition. Calculate earliest and latest times for the unconstrained model, then produce a separately labelled feasible schedule with the stated resources.
Ask for a predecessor check, assumptions and intermediate calculations. Do not let the model invent approvals, staff availability or a public completion promise.
Contents · Previous chapter · Next chapter
19. Independently verify the schedule
Check each task’s finish equals its start plus its duration. Check every successor starts no earlier than all required predecessors finish, and confirm that incompatible assignments do not overlap.
Verify the final milestone and recompute after any change. A polished timeline can conceal impossible handoffs, so inspect the underlying relationship table.
Contents · Previous chapter · Next chapter
20. Distinguish an estimate from a commitment
The 12-hour result is conditional on assumed durations, continuous working time and sufficient resources. Actual work may encounter review delays, interruptions or changed requirements.
A responsible coordinator can adopt a separately reviewed commitment with appropriate contingency. The critical path calculation does not guarantee the date or define the right amount of contingency.
Contents · Previous chapter · Next chapter
21. Maintain a baseline and an updated schedule
Record the initial activity list, durations, dependencies, resource assumptions and finish estimate. When a task begins or finishes, use actual status to update the remaining work rather than overwriting the original plan.
Comparing the baseline and revised schedule helps identify why the forecast changed. Preserve the evidence for actual completion and approval, not merely the originally expected finish.
Related guide: decision-sensitive assumptions.
Contents · Previous chapter · Next chapter
22. Practise with a changed network
A fictional project has X taking two hours, then Y taking four and Z taking two in parallel. W takes one hour after both. With sufficient resources the finish is 2 + max(4,2) + 1 = 7 hours.
Z has two hours of total float in this simplified model. Now add three hours to Z and independently calculate the new finish of eight hours. Explain why the controlling branch changes.
Contents · Previous chapter · Next chapter
23. Connect scheduling across zoom levels
A student can map prerequisites for a project, a teacher can sequence resource preparation and a team can coordinate interdependent deliverables. Larger organisations need appropriate scheduling expertise, resource planning and risk assurance.
The shared idea is to identify what determines delivery instead of treating all tasks as equally controlling. The network must reflect the scale and consequences of the work.
Contents · Previous chapter · Next chapter
24. Connect vocabulary, Ztime and EnDist
Vocabulary Coding and Engineering distinguishes duration, effort, predecessor, readiness, critical path, float and commitment. Ztime preserves the schedule’s version and actual status so a later reader can reconstruct why the forecast changed.
EnDist is a conceptual lens for useful forward progress after misunderstanding and rework, not physical energy or a validated numerical metric. Correctly sequencing dependencies may reduce avoidable delay but does not prove universal efficiency.
Read more: shared vocabulary · EnDist in Civilisation OS.
Contents · Previous chapter · Next chapter
25. Four weeks of practice
Week one: write a six-task fictional dependency network and verify the finish definition. Week two: calculate earliest and latest times, then test the effects of delays on both branches.
Week three: add a resource conflict and compare feasible schedules. Week four: prepare a versioned baseline and updated forecast, then practise a different network independently before asking AI to check it.
Contents · Previous chapter · Next chapter
26. Questions beginners ask and the next useful step
Is the longest individual task always critical? No. Can there be several critical paths? Yes. Can float be spent twice? Not necessarily. Does a calculated finish guarantee delivery? No.
Start with the next small project you need to coordinate. Write what must finish before each task starts, and calculate which sequence controls the outcome before asking AI to make the project faster.
The US Government Accountability Office’s Schedule Assessment Guide describes sound activity sequencing, resource assignment, critical paths, schedule flexibility and updating schedules. This simplified fictional activity network illustrates selected concepts and is not a substitute for professional scheduling or risk analysis.
Contents · Previous chapter · Revisit the start of this collection
