VIEW THIS AS

Auto mode follows the Route Engine until you choose a viewpoint.

YOU ARE HERE

ROUTE CHECK

CONNECTED TO

WHAT NEXT

Use the canonical route for this room, or HELP if you are unsure.

Top 100 Vocabulary for Adults | Quantity Surveyors & Cost Consultants

Top 100 Vocabulary for Adults | Quantity Surveyors & Cost Consultants

Quantity-surveying vocabulary is the language of measuring, forecasting and controlling the money inside construction. Quantity surveyors and cost consultants translate designs into cost plans, contracts into valuations, and project change into commercial consequences.

This professional flagship belongs to the eduKate Adult Vocabulary for Professionals system. It complements Construction Management Professionals, Facilities Management Professionals and Property Management Professionals.

The Four Banks

Measurement & Estimating: measurement, quantity, take-off, dimension, rate, unit rate, estimate, elemental estimate, cost plan, benchmark, area rate, preliminaries, overhead, profit, contingency, escalation, inflation, allowance, provisional sum, prime cost sum, risk allowance, lifecycle cost, value, budget, cost limit.

Tendering & Contract: bill of quantities, specification, tender, tenderer, invitation to tender, addendum, clarification, tender return, tender analysis, normalisation, bid, contract sum, form of contract, scope, package, procurement route, lump sum, remeasurement, design and build, subcontract, bond, insurance, retention, liquidated damages, acceptance.

Valuation & Change: valuation, progress claim, payment application, payment certificate, work completed, materials on site, variation, change order, daywork, instruction, omission, addition, rate build-up, star rate, quotation, loss and expense, prolongation, disruption, extension of time, claim, entitlement, substantiation, notice, assessment, certification.

Cost Control & Closeout: committed cost, actual cost, forecast cost, cost report, variance, cash flow, accrual, contingency drawdown, risk register, value engineering, cost saving, cost avoidance, reconciliation, final account, settlement, defect, retention release, lifecycle, whole-life cost, operating cost, capital cost, benchmarking, audit, commercial governance, cost certainty.

Top 100 Quantity Surveying Vocabulary: Working Meanings

#WordProfessional meaning
1MeasurementThe quantified assessment of construction work.
2QuantityThe measured amount of an item or work category.
3Take-offThe extraction of quantities from drawings or models.
4DimensionA measured length, area, volume or other extent.
5RateA price applied to a unit of measured work.
6Unit rateThe cost assigned to one unit of quantity.
7EstimateA projected cost based on available information.
8Elemental estimateAn estimate organised by building elements.
9Cost planA structured allocation of project budget across elements.
10BenchmarkA reference cost drawn from comparable projects or data.
11Area rateA cost estimate expressed per unit of floor area.
12PreliminariesProject-wide costs not directly tied to one permanent work item.
13OverheadIndirect business or project cost.
14ProfitThe financial return remaining after costs.
15ContingencyA reserve for uncertain or unforeseen costs.
16EscalationIncrease in cost over time due to market or inflationary effects.
17InflationGeneral increase in price levels over time.
18AllowanceA provisional amount included for anticipated cost.
19Provisional sumAn allowance for work not sufficiently defined at contract stage.
20Prime cost sumAn allowance for the supply cost of a specified item under certain contract forms.
21Risk allowanceA cost provision for identified project uncertainty.
22Lifecycle costCost considered across acquisition, operation, maintenance and disposal.
23ValueThe relationship between benefits, performance and cost.
24BudgetThe planned financial allocation for the project.
25Cost limitThe maximum approved project cost.
26Bill of quantitiesA structured document listing measured work items and quantities.
27SpecificationWritten requirements defining materials, workmanship and performance.
28TenderA formal offer to carry out work for a stated price and terms.
29TendererA party submitting a tender.
30Invitation to tenderA formal request for contractors to submit bids.
31AddendumAn official amendment issued during tender.
32ClarificationAdditional information resolving tender ambiguity.
33Tender returnThe submitted bid package from a tenderer.
34Tender analysisStructured comparison of submitted bids.
35NormalisationAdjustment of bids to a common basis for fair comparison.
36BidA commercial offer for specified work.
37Contract sumThe agreed monetary amount under the construction contract.
38Form of contractThe standard contractual framework governing rights and obligations.
39ScopeThe boundaries of work included in the contract.
40PackageA defined group of works procured together.
41Procurement routeThe organisational and contractual method used to deliver a project.
42Lump sumA fixed total price for a defined scope, subject to contract terms.
43RemeasurementA contract approach where payment reflects actual measured quantities.
44Design and buildA procurement arrangement where one party takes responsibility for both design and construction.
45SubcontractA contract for a specialist portion of the main works.
46BondA financial security supporting contractual performance.
47InsuranceFinancial protection against specified project risks.
48RetentionA portion of payment withheld as contractual security.
49Liquidated damagesPre-agreed damages for specified delay where enforceable.
50AcceptanceFormal agreement to a tender or contractual offer.
51ValuationAn assessment of the value of work completed.
52Progress claimA contractor request for payment based on progress.
53Payment applicationA formal submission requesting interim payment.
54Payment certificateA formal certification of the amount due.
55Work completedThe measured value of construction work properly executed.
56Materials on siteMaterials delivered and potentially eligible for valuation under contract terms.
57VariationA change to contracted scope, quantity or design.
58Change orderA formal instruction modifying contracted work.
59DayworkWork valued using recorded labour, materials and plant rather than pre-agreed quantities.
60InstructionA formal direction affecting contracted work.
61OmissionRemoval of work from the contracted scope.
62AdditionExtra work added to the contracted scope.
63Rate build-upA calculation showing components making up a unit rate.
64Star rateA newly derived rate used when no suitable contract rate applies.
65QuotationA formal price offered for changed or additional work.
66Loss and expenseAdditional cost claimed due to qualifying disruption or delay under contract terms.
67ProlongationAdditional project cost caused by extended duration.
68DisruptionLoss of productivity or efficiency caused by interference with planned work.
69Extension of timeAn approved adjustment to contractual completion time.
70ClaimA formal request for additional money, time or contractual relief.
71EntitlementThe contractual basis supporting a claim.
72SubstantiationEvidence supporting the amount or basis of a claim.
73NoticeA formal communication required under contract procedures.
74AssessmentProfessional evaluation of cost or claim value.
75CertificationFormal confirmation of an assessed contractual amount.
76Committed costCost contractually committed but not necessarily paid.
77Actual costCost already incurred.
78Forecast costEstimated future project cost.
79Cost reportA structured summary of budget, commitments, actuals and forecast.
80VarianceThe difference between planned and actual or forecast cost.
81Cash flowThe timing of money entering and leaving the project.
82AccrualA cost recognised before the related invoice or payment occurs.
83Contingency drawdownThe approved use of contingency funds to cover defined cost.
84Risk registerA structured record of cost and project risks.
85Value engineeringSystematic adjustment of design to improve cost-value balance.
86Cost savingA measurable reduction in expected expenditure.
87Cost avoidanceAction preventing an otherwise likely future cost.
88ReconciliationComparison and alignment of cost data from different stages or sources.
89Final accountThe agreed final value of works after all adjustments.
90SettlementAgreement resolving outstanding commercial amounts or claims.
91DefectWork that fails to meet required standard or specification.
92Retention releasePayment of retained sums after contractual conditions are met.
93LifecycleThe full period from construction through operation and end-of-life.
94Whole-life costTotal cost over acquisition, operation, maintenance and disposal.
95Operating costOngoing expenditure required to run an asset.
96Capital costUpfront expenditure required to create or acquire an asset.
97BenchmarkingComparison of cost against relevant reference data.
98AuditA structured review of commercial records and controls.
99Commercial governanceThe system of authority, approvals and controls governing project cost.
100Cost certaintyThe degree of confidence that final project cost will remain within the approved range.

Cheap Is Not the Same as Good Value

A lower tender can hide exclusions, unrealistic allowances or future maintenance cost. Cost consultants compare scope, quality, risk and whole-life consequences, not price alone.

Scenario: The Lowest Tender Is 15% Below the Others

Normalise the bids. Check omissions, qualifications, provisional sums, productivity assumptions and whether the bidder misunderstood the scope. A suspiciously low number may become an expensive contract later.

Seven-Day Quantity Surveying Vocabulary Plan

DayPractice
1Measure a simple work package and build unit rates.
2Build an elemental cost plan with contingency.
3Normalise three hypothetical tender returns.
4Value a variation from instruction to certification.
5Build a cost report with forecast and risk.
6Recall 75+ quantity-surveying terms.
7Write a one-page commercial review linking scope, change, cash flow and final cost.

Continue the Construction & Operations Wing

Conclusion

Quantity-surveying vocabulary helps professionals make construction economics visible. It connects measurement, procurement, valuation, change and closeout into one disciplined language of cost and contractual value.

Discover more from eduKate Singapore

Subscribe now to keep reading and get access to the full archive.

Continue reading